    Do the specified costs (tube bends, cuts, end preps) also require assembly time or is that incorporated into their costs?

    ie i have frame tubes that are bent, but does it also require an assembly entry for the time it took to make that bend?

    Ben Beacock
    Chassis Design and Technical Coordinator
    Gryphon Racing - University of Guelph

  2. #2
    Do the specified costs (tube bends, cuts, end preps) also require assembly time or is that incorporated into their costs?

    ie i have frame tubes that are bent, but does it also require an assembly entry for the time it took to make that bend?

    Ben Beacock
    Chassis Design and Technical Coordinator
    Gryphon Racing - University of Guelph
    Ben Beacock
    Alumni
    '03,'04(AWD),'05(AWD) Gryphon Racing - University of Guelph

  3. #3
    <BLOCKQUOTE class="ip-ubbcode-quote"><font size="-1">quote:</font><HR> Do the specified costs (tube bends, cuts, end preps) also require assembly time or is that incorporated into their costs?

    ie i have frame tubes that are bent, but does it also require an assembly entry for the time it took to make that bend? <HR></BLOCKQUOTE>

    I understood the assembly costs as what it takes to put two parts together. In your case, I would say that the bent tube is a component. If you welded something to that tube, the weld would be part of the assembly cost.

    The tube segment itself has no assembly time.